ourprojects


Clean Harbours Canada

Dundas Waste Water Treatment Plant

Market: Environmental
Owner: Clean Harbours Canada
Consultant: Myley Company Ltd.
Client: Clean Harbours
Lockerbie & Hole
Location(s): Thorold, ON
Contract Type: Fixed Price
Contract Value: $760,000
Project Duration: 10 Months
Project Status: Complete



Clean Harbours Niagara transfer, recycling and processing facility located in Thorold, ON was expanded in 2004 to support the recycling of lithium batteries.

Raven Construction was responsible for civil and architectural activities associated with the expansion of the facility, specifically the Hydrolysis Unit and Storage Building. Our scope included:

  • Excavation and backfill for utility trenches and firewater system
  • Installation of underground firewater lines and fire hydrants
  • Cast-in-Place concrete foundations and building floor slab
  • Construction of new plant access roads
  • Installation of perimeter fencing
  • Cladding installation
Highlights

  • Concrete and underground firewater line installation commenced in November of 2003, resulting in all work being completed during winter months. Heating and hoarding systems required to ensure project quality standards were maintained.
  • Project took place within an operating facility. Additional coordination required with plant personnel to ensure that construction activities did not impact plant production.